Potsdam hydro plant. Photo: Village of Potsdam.
Potsdam hydro plant. Photo: Village of Potsdam.

Potsdam gets $6.8 million judgment for hydro-plant losses

The state Supreme Court has ruled that the village of Potsdam is owed $6.8 million by a Canadian hydro-turbine manufacturer. Canadian Turbines of Ontario signed a contract with Potsdam in 2007 to deliver parts for the village's new hydro-power project on the Raquette River. The parts were supposed to be delivered by mid-2008.  Go to full article